A renovation timeline — what happens when, and who to book


A renovation is not one job. It is a dozen jobs by different people, each of which can only start when the one before it is done, plus a stream of deliveries that have to arrive on the right day — not too early, because there is nowhere to put a fridge in a room without a floor, and not too late, because the fitter is booked.

The timeline below is the usual order of the work. Your renovation will skip some steps and repeat others; the order is what matters.

1. Measure, decide, and ask for quotes

Before anything is booked, know what you are doing in each room and what goes in it. Measure properly — every wall, window and doorway — and keep the measurements with the project, not on the back of an envelope.

Ask more than one contractor for a quote on the same list, so the quotes can be compared. A quote that is much cheaper usually leaves something out; read what is included before what it costs.

2. Order what takes longest

The longest wait in a renovation is often not the work but the things the work needs. Made-to-measure kitchens, worktops cut to size, built-in wardrobes, windows and some tiles can take weeks to arrive. Order them early — often before the room they belong to has been touched — and write down the delivery date you were promised.

3. Strip out and prepare

Old kitchens, floors and fittings come out; walls are opened where needed. This is when the surprises appear: wiring that has to be replaced, damp, uneven floors. Take photographs of what you find before anything is covered up again. They settle arguments later and help whoever comes next.

4. First fix — the work inside the walls

The electrician and the plumber run cables and pipes and fit the boxes and connections that will end up behind the walls and under the floors. Air conditioning ducting goes in now too. It is the work nobody sees afterwards, which is why it must be checked before the walls are closed.

5. Walls, ceilings and floors

Plastering or skimming, then ceilings, then floors and tiling. Each needs time to dry or set before the next can start, so this stage is where a timeline most often slips. Book the trades in order, and leave the drying time between them.

6. Fit out — kitchens, bathrooms, carpentry

Cabinets, worktops and wardrobes are installed, sanitaryware is fitted, carpentry is finished. This is when the deliveries ordered in step 2 must arrive — on the right day, into a room that is ready for them.

7. Second fix and paint

The electrician comes back to fit switches, sockets and lights; the plumber connects taps and appliances. Then painting, usually last, so nothing scuffs a finished wall.

8. Clean, install the furniture, hand over

A proper clean, then the loose furniture, curtains and blinds. Finally the handover: walk through every room with whoever did the work, write down what is not right, and agree when it will be fixed. Photograph each point you agree on.

What holds a timeline together

Three things, whatever you use to keep track:

  • Every date in one place. Deliveries, the days things are installed, the electrician's two visits, the tiler, the deadline for the painting. A delivery date in one email and the fitter's date in another is how a fridge arrives in a room with no floor.
  • Who must be there. Each visit needs someone to open the door and answer questions. Decide who, and tell them — and tell them again if it moves.
  • Sign-off before the next step. A job is done when you have looked at it, not when someone says it is. Before-and-after photos and a clear "approved" stop half-finished work from being covered up by the next trade.
The YPReno Schedule: the coming days' appointments and deliveries in one list that starts today — an electrician's final check, a showroom visit, a cabinet delivery with its confirmed date, and curtain measuring.
One schedule for the visits, the deliveries and the deadlines — starting with today.

Where this leads

If the money is the part that worries you, start with how to set a renovation budget you can actually keep. To see how YPReno keeps deliveries, installations, appointments and task deadlines on one schedule — and in your own phone's calendar — see schedule and tasks, or start free.

Common questions

How long does a home renovation take?

It depends on the size of the home, how much is being changed, and how long the things you order take to arrive — which is often the longest wait of all. Ask each trade for the time their part needs and the time the materials need, and plan from the longest one.

What should be ordered first?

Anything made to measure or with a long lead time: kitchen cabinets, worktops, built-in wardrobes, special tiles, windows. They often need to be ordered before the work they belong to even starts.

When should the electrician come?

Usually twice: once early, before walls are closed and painted, to run the cables and fit the boxes; and once near the end, to fit the switches, sockets and lights. Book both visits when you plan the work.

What is a handover?

The visit where you walk through the finished work with whoever did it, note anything that is not right, and agree when it will be fixed. Do it with a list, in daylight, and keep photographs of what you agreed.